ISO 9001:2008 Certified Company
TAM Completion Systems
Home > Oil & Gas Applications > Zonal Isolation > Water Shut off > Water Shut Off - Vertical
Water Shut Off - Vertical
contact_icon.gif  Contact Us    
ipad_icon.gif  Request for Application Analysis  

Water Shut Off - Vertical

Requirement:

  • Open hole, vertical completion producing excess water

Solution:
  • Run Inflatable Bridge Plug (IBP) on work string
  • Place cement plug above IBP
  • Restore well to production

 

 case_study.gif

West Texas:

Challenge:
  • An oil field producing from a reef type carbonate formation exhibits a continual rise in the oil/water contact.
  • Wells are vertical, open hole completions at an average depth of 2,500’ and the field has both water and gas injection for pressure maintenance and improved recovery.

Solution:
  • An inflatable bridge plug  was run and set 5’ above the O/W contact and a 5’ cement plug placed above the IBP.

Value Added:
  • The well was returned to production with water cut reduced from 90% down to 10% and total fluid production increased by more than 1,000 BPD.
  • The workover was achieved using a hydraulic snubbing unit to minimize formation damage typically associated with loss of produced brine into the high permeability formation.
  • Some wells were completed without the cement plug to allow moving and repositioning the tool as the OW contact rises.

 

 
 